Maidenhead Waterways Weir Complex

Maidenhead, Berkshire

Maidenhead Waterways Weir Complex

Background

Construction of a reinforced concrete weir to lift and stabilise the water levels in channels running through Maidenhead Town Centre, making it accessible for small boats and other water related activities.

The works included lining the waterway bed to connect it to previous channel works, provision of a landscaped wetland area and installation of bank retention to leave a natural edge to the waterway. The weir complex includes a fish and eel pass and boat rollers.

Our Services

Appointed from the outset of the project, our pre-contract services included:

  • Providing advice on procurement routing;
  • Completion of the tender process; and
  • Compilation of the contract.

Throughout the construction process, our responsibilities included:

  • Project management, as per the NEC4 contract;
  • Providing advice alongside issuing project manager’s instructions;
  • Commercial advice;
  • Preparation of interim valuations;
  • Preparation of monthly cost reports;
  • Assessment of compensation events; and
  • Conclusion of the contractual requirements including issuing and checking defects schedules.

Sean Ellison


Maidenhead Waterways Weir Complex

Maidenhead, Berkshire

Maidenhead Waterways Weir Complex

Maidenhead Waterways Weir Complex panel

Background

Construction of a reinforced concrete weir to lift and stabilise the water levels in channels running through Maidenhead Town Centre, making it accessible for small boats and other water related activities.

The works included lining the waterway bed to connect it to previous channel works, provision of a landscaped wetland area and installation of bank retention to leave a natural edge to the waterway. The weir complex includes a fish and eel pass and boat rollers.

Our Services

Appointed from the outset of the project, our pre-contract services included:

  • Providing advice on procurement routing;
  • Completion of the tender process; and
  • Compilation of the contract.

Throughout the construction process, our responsibilities included:

  • Project management, as per the NEC4 contract;
  • Providing advice alongside issuing project manager’s instructions;
  • Commercial advice;
  • Preparation of interim valuations;
  • Preparation of monthly cost reports;
  • Assessment of compensation events; and
  • Conclusion of the contractual requirements including issuing and checking defects schedules.

Sean Ellison


Back