Background

Construction of a new access road at Site 6, Sovereign Harbour to enable access to a new community centre.

Our Services

Base Quantum was appointed to provide quantity surveying services from pre-construction through to post-construction, working with the consultant design and engineering team. Our team were able to apply expertise that contributed to the successful delivery of the access road, on time and on budget. Responsibilities included:

  • Preparing the cost plan and developing the scheme budget;
  • Preparation of the tender pack;
  • Analysis of tender returns and recommendation of a suitable contractor;
  • Reviewing monthly contractor valuations;
  • Assessing change under the contract;
  • Maintaining cost reporting; and
  • Preparing and agreeing final account.

Laura Hannan


Sovereign Harbour Access Road

Eastbourne, East Sussex

Sovereign Harbour Access Road main

Sovereign Harbour Access Road panel

Background

Construction of a new access road at Site 6, Sovereign Harbour to enable access to a new community centre.

Our Services

Base Quantum was appointed to provide quantity surveying services from pre-construction through to post-construction, working with the consultant design and engineering team. Our team were able to apply expertise that contributed to the successful delivery of the access road, on time and on budget. Responsibilities included:

  • Preparing the cost plan and developing the scheme budget;
  • Preparation of the tender pack;
  • Analysis of tender returns and recommendation of a suitable contractor;
  • Reviewing monthly contractor valuations;
  • Assessing change under the contract;
  • Maintaining cost reporting; and
  • Preparing and agreeing final account.